Sunday, July 12
Yeah! The subfloor for the addition is laid. Lumber for the addition walls was delivered Friday
and is stacked on the floor. We are watching the weather and hoping for two days without rain to get the walls framed. We seem to be getting rain every few days so we work around it.
Joe has started on the plumbing and I finished the insulation on the front exterior wall. Because of the uneven spacing of the studs on the one wall, I have had to special cut each piece of insulation so this one wall has been time consuming. The other walls have studs that are pretty much the same spacing so the insulation should go in much quicker.
It seems like there are several projects going on simultaneously . Thank goodness Joe is so organized.